Requisition supplement planning is only available if project default ZP_MS_SUPP is set to Y or E. If the project default is set to E, the supplement planning is enforced, that means that at least one supplement plan must exist for each planned requisition.
-
Click the Planning task on the dashboard, or select Planning from the Tasks list.
-
Select a requisition planning item in the tree.
-
Click Planning to display the Planning section.
-
Select the Milestones tab.
-
Click Add Supplement Plan
to add a requisition supplement plan.
-
Type the supplement number in the Suppl box.
-
Select Purchase if the requisition should be used to create an agreement, or do not select the check box if the requisition is for inquiry only.
-
Click ROS Date
and select the date when the material is required on site.
If a requisition is linked to the plan, the minimum ROS date of the requisition line items is displayed. This ROS date can only be changed, if project default ZP_MS_ROS is set to Y.
-
Type a value in the Lead Time box.
The lead time value is interpreted as weeks by default. This can be changed in the M_PCK_MS_CUSTOM.CALC_PLANNED_ISSUE_DATE CIP.
The Planned Issue date is calculated as ROS Date - Lead Time, and this date cannot be changed.
-
Click Save.
-
Click the requisition number to edit the milestones (see Edit milestone planning).