To maintain milestone dates of planned tagged items or planned requisitions in a data grid, you can view a milestone summary by milestone set.
The milestone summary does not consider any supplements.
-
Click the Planning task on the dashboard, or select Planning from the Tasks list.
-
Select Group By - Milestone Set from the drop-down list on top of the left navigation panel.
-
Select the milestone set for that you want to view the summary.
All planning items assigned to the set are displayed in a grid, with planned, forecasted, and actual dates for all milestones.
-
A completed milestone (actual date is set) is highlighted with
in the Status column.
-
A milestone with critical delay (the actual date is not set, and the planned date is in the past) is highlighted with
in the Status column.
-
The actual date is highlighted with
if it exceeds the deadline (planned and/or forecasted date).
-
-
Select a planning item, and edit the dates as required.
-
Click the planning item in the first cell to view the planning item details.
You can change the read-only state of a date in the milestone planning (see Edit milestone planning).