If supplier integration (via Jovix) is enabled (project default ZI_JX_SWCH is set
to Yes and ZI_JX_INT is set to A), with the approval the ownership/control of the
agreement is automatically passed to the associated supplier. This is indicated by
the enabled Recall From Supplier button.
-
Click the Agreements task on the dashboard.
-
Select an agreement.
-
Click the Approve button.
If multi-step approval is required, see Perform multi-step approval.
The Approve button is not enabled if any of the following apply:
-
The supplement is not the highest supplement of the agreement.
-
The agreement is closed.
An agreement is closed, if the Closed date is set and the ZP_CONSCLS project default is set to Y.
-
The supplement is approved.
-
An approval sequence is defined for the supplement.
-
The agreement is a Notice to Proceed subcontract.
-
The project default ZP_ADV_APP is set to Y, and the Ready for Approval indicator is not set.
-
You do not have the required approval rights, that means, you do not have one or more of the following privileges:
-
NOC APPROVAL - required to approve agreements of type Notice of Commitment.
-
SM APPROVAL - required to approve agreements of type Subcontract, Work Order, Service Agreement, or Subcontract Notice of Commitment.
-
BO APPROVAL - required to approve agreements of type Blanket Order or Master Agreement.
-
PO APPROVAL - required for the approval of all other agreement types.
-
-
The ERP Managed check box is selected and you do not have the PROCESS ERP AGREEMENTS/REQS privilege.
If any changes are applied to the selected agreement supplement, the Approve button is deactivated.
-