Enter a planned date for one milestone.
-
If you enter more than one planned date, the recalculation will consider only the value of the milestone with the lowest sequence. All other values will be overwritten.
-
For a two-phase planning, you must enter a date in the 1st phase (between first milestone and 1st pass milestone) and a date in the 2nd phase (between 2nd pass milestone and the last milestone).
-
-
If the plan has changed from the original plan, update the values in the Days cell accordingly.
-
Click Save.
-
Click Select an Option
.
-
Click Recalculate Planned Dates.
The planned dates are calculated based on the entered date(s) + span days + add days.
To delete the planned dates, click Select an Option
> Clear Planned Dates.