Click the Planning task on the dashboard, or select Planning from the Tasks list.
-
Click Add Planning Item
to create a new planning item, then select Tag from the Planning Item Type list.
Alternatively, after selecting the Group by - Type option and selecting Tag Number in the tree, click Add Planning Item
in the Tag Numbers grid.
-
Type or select a tag number from the list in the Tag Number box.
-
Click Milestone Set
and select a milestone set.
-
(Optional) Click ROS Date
and select the required on site date.
-
(Optional) Type the client requisition number in the Client Requisition Number box.
-
(Optional) Click Account Code
and select an account code.
-
(Optional) Type the client agreement number in the corresponding box.
-
(Optional) Click Planning Group
and select a planning group.
-
(Optional) Type the budget values in the Labor Budget 1 and Labor Budget 2 boxes.
-
(Optional) Type a comment on the planning item in the Comments box.
-
Click Save.