Recall agreement back from supplier - Intergraph Smart Materials - 10.4 - Help - Hexagon

Intergraph Smart Materials Help (10.4)

ft:locale
en-US
Product
Intergraph Smart Materials
Subproduct
(WPF)
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.4

If supplier integration (via Jovix) is enabled (project default ZI_JX_SWCH is set to Yes and ZI_JX_INT is set to A) and you have the ALLOW SUPPLIER INTEGRATION privilege, you can revert back the ownership of an agreement from the associated supplier.

  1. Click the Agreements task on the dashboard.

  2. Select an agreement with ownership transferred to Jovix.

  3. Click Recall From Supplier.

    The button is only enabled if

    • project default ZP_CONSCLS is set to N, or ZP_CONSCLS is set to Y and the Close Date is not set

    • the agreement is not controlled by an ERP system, or you have the PROCESS ERP AGREEMENTS/REQS privilege

    • the ownership of the agreement is currently with Jovix