On the Subcontract Status panel, you can edit the subcontract status information.

If project default ZP_SMINCPO is set to N (default), this panel is only displayed for change orders of a subcontract agreement. If ZP_SMINCPO is set to Y, this panel is available for all change orders.

The Original Substantial Completion displays the original completion date of the substantial activity of the SOW (scope of work) milestone.

The Current Substantial Completion displays the current completion date of the substantial activity (date of the substantial activity + days of the approval schedule days of all assigned change order requests).

The Original Final Completion displays the original completion date of the final activity of the SOW milestone.

The Current Final Completion displays the current completion date of the final activity (date of the final activity + days of the approval schedule days of all assigned change order requests).

The sum of all approved schedule change days of all assigned change order requests (CORs) of the change order (CO) appears in the CO Time Change Days box.

The sum of all approved schedule change days of all assigned CORs of all COs, beginning with the actual CO to the first CO of the agreement, appears in the Total Time Change Days box.

  1. Click Subcontract Status on the category panel.

  2. Click Subcontract Status Com_LOV_Add ICON and select the subcontract status.

  3. In the CO Summary box, type the description of the change order (CO).