CALC_PLANNED_ISSUE_DATE - Intergraph Smart Materials - Version 10.1 - Customization & Programming - Hexagon

Intergraph Smart Materials Customization (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Customization & Programming
Smart Materials/Smart Reference Data Version
10.1

Description:

This procedure calculates the planned issue date for supplement milestone plans of planned requisitions. Depending on the implementation, the value returned by the calculation can be interpreted as days or weeks (default).

Type:

Function

Usage:

P.60.03

Event:

Performed for each record in the Planned Supplements block.

Default:

m_pck_calendar.calc_work_day(TRUNC(p_ros_date),(p_lead_time*7))