Purpose

This section explains how to issue the approved agreement to the supplier/subcontractor.

Exercise

  1. Open the P.50.01 Agreements screen from the Smart Materials > MSCM > P.50 Agreements (Orders/Subcontracts) menu branch.

  2. Click the Run Query button to display the available agreements.

  3. Select the TRAINPROJ-PO-15 agreement and double-click in the Agreement Number field. The P.50.07 Maintain Agreements screen opens.

  4. On the Agreement tab, click the Issue button.

    The Issue button is only enabled if the agreement is approved.

    The current date appears in the Issued field.

  5. Close the screen by selecting File > Close All or Close from the main menu.