The following table shows approval sequences and their associated settings.

Screen

Approval template

Privilege

Filled from...

Started by...

P.20.01 Suppliers/Subcontractors, Qualifications tab

Qualification

ALLOW SUPPLIER APPROVAL

P.10.25 Question List: assigned approval sequence

Submit

P.20.02 Login Requests

Login Request

ALLOW SUPPLIER APPROVAL

DBA setting: LOGIN_REQUEST_APT

Submit

P.20.04 Company Profile

Company Profile

ALLOW SUPPLIER APPROVAL

P.10.25 Question List: assigned approval sequence

Submit

R.30.01 Maintain Requisitions

Engineering Requisition

ER APPROVAL

No

RfA check box

P.30.21 Prepare RFQ, Bidders tab

Bidder

ALLOW SUPPLIER APPROVAL

No

Request Bidder Approval check box

P.30.21 Prepare RFQ, Addenda tab

Addendum

ALLOW INQUIRY APPROVAL

No

Manually

P.30.21 Prepare RFQ, Inquiry tab

Inquiry

ALLOW INQUIRY APPROVAL

No

Inquiry RfA check box

P.30.22 Commercial Evaluation, Quote Summaries tab

Quote Summary

QUOTE APPROVAL

No

Quote RfA check box

P.50.07 Maintain Agreements

Purchase Order

PO APPROVAL

No

Ready for Approval check box

SM.20.11 Subcontract Administration, Item Progress tab

Work Progress

PROGRESS APPROVAL

Project default: ZP_APRWKP

Submit

SM.20.11 Subcontract Administration, Schedule of Values tab

Schedule of Values

SOV APPROVAL

Project default: ZP_APRSOV

Submit

SM.20.11 Subcontract Administration, SOV Progress tab

Schedule of Value Progress

PROGRESS APPROVAL

Project default: ZP_APRSVP

Submit

SM.20.11 Subcontract Administration, Milestone Summary tab

Milestone Progress

PROGRESS APPROVAL

Project default: ZP_APRMSP

Submit

SM.20.11 Subcontract Administration, Invoices tab

Invoice

INV APPROVAL

No

Manually

SM.30.07 Non Conformance Reports

Non Conformance Reports

NCR APPROVAL

No

Ready for Approval check box

SM.40.02 Change Order Requests

Change Order Request

COR APPROVAL

Project default: ZP_APRCOR

Ready for Approval check box

SM.40.05 Back Charges

Back Charges

BC APPROVAL

No

Manually