You can specify different kinds of subcontract information, including subcontract statuses, categories, reason codes, and bond/surety types on the SM.10 Setup screens.

SHARED Tip Like other areas of Smart Materials, the setup screen numbers correspond to where the setup information is used. For example, the data on SM.10.41, 42, and 43 is used on the SM.40.01 Potential Change Orders screen.

Enter subcontract status, categories, and reason codes

  1. In the menu tree, navigate to Smart Materials > Site > Subcontract Management.

  2. Double-click SM.10 Setup.

  3. On the SM.10.41 SC Status, SM.10.42 SC Categories, and SM.10.43 Reason Codes screens, specify information for subcontracts as needed.

Enter bond/surety types

  1. In the menu tree, navigate to Smart Materials > Site > Subcontract Management.

  2. Double-click SM.10 Setup.

  3. On the SM.10.12 Bond/Surety Types screen, specify the information for bond and surety types.

Enter notice types

  1. In the menu tree, navigate to Smart Materials > Site > Subcontract Management.

  2. Double-click SM.10 Setup.

  3. On the SM.10.32 Notice Types screen, specify the information for notice types.