Hand-Over Dates - Intergraph Smart Materials - Version 2020 (10.0) - Help - Hexagon PPM

Intergraph Smart Materials Classic Help (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Help
Smart Materials/Smart Reference Data Version
2020 (10.0)

The Hand-Over Destination field displays the name of the destination (in the routing method) that has been marked as 'Hand-Over Point.' If this destination represents the contractual delivery date, the background color of this field is set to magenta. A destination marks the contractual delivery date if the Delivery Date check box has been set for it on the P.10.53 Routing Methods screen. You can double-click in this field to open the Expediting Dates window, which provides a tabular view of all expediting dates. For more information, see Expediting Dates.

The Hand-Over Planned field shows the planned date of the destination (in the routing method) that has been marked as ‘'Hand-Over Point.' You can double-click in this field to open the Expediting Dates window.

The Hand-Over Forecasted field shows the forecasted date of the destination (in the routing method) that has been marked as 'Hand-Over Point.' If the forecasted date has been set manually, it is highlighted by a cyan background color. You can double-click in this field to open the Expediting Dates window.

The Hand-Over Actual field shows the actual date of the destination (in the routing method) that has been marked as 'Hand-Over Point.' You can double-click in this field to open the Expediting Dates window.