On the SOW Milestones tab, you can see all SOW milestones attached to the inquiry.

This folder is only available for subcontracting inquiries.

The Start Work field shows the date of the start activity, with the corresponding activity in the Start Activity field. You can double-click in this field to open the J.30.01 Activities screen where activities are defined.

The Substantial Completion field shows the date of the substantial activity, with the corresponding activity in the Substantial Activity field. You can double-click in this field to open the J.30.01 Activities screen where activities are defined.

The Final Completion field shows the date of the final activity, with the corresponding activity in the Final Activity field. You can double-click in this field to open the J.30.01 Activities screen where activities are defined.

In the next (Interim Milestones) block, you can see all SOW milestone details (interim milestones) attached to the inquiry.

The order sequence of the interim milestone is shown in the Seq field.

The Interim Milestone field shows the description of the interim milestone.

The name of the activity assigned to the interim milestone is displayed in the Activity Code field. You can double-click in this field to open the J.30.01 Activities screen where activities are defined.

The Date field shows the date of the activity. You can double-click in this field to open J.30.01.

You can double-click in this field to open the J.30.01 Activities screen.