The BOM options include Best Quantity, Use Only Site Status, Only Endnodes, Issue Status, and List Status.

Select the Best Quantity indicator to use the best quantity logic. If the indicator is not checked, you must select an issue status from the LOV in the Issue Status field. The Use Only Site Status option is used in conjunction with Best Quantity. If you select this option, only those statuses that are marked as Use on Site on B.10.08 are considered; the others are ignored.

Select the Only Endnodes check box when only terminal BOM nodes should be processed by the FR/RR. The default behavior is to process all nodes with the check box not selected.

Select the list status from the LOV in the List Status field.