In the menu tree, navigate to Smart Materials > MSCM > P.50 Agreements (Order/Subcontracts), and double-click P.50.01 Agreements.
-
On P.50.01 Agreements, enter a query, and then double-click an order in the Order Number column. The software displays P.50.07 Maintain Agreements: Window 2.
-
Click the Scope of Work tab.
-
In the SOW Section box, click List of values .
-
Browse to select a SOW section, and click OK. Repeat until you have added all the necessary sections.