Is screen P.30.03 to be called always?

If you want screen P.30.03 Inquiry Assignment to be called in all cases, you have to set this project default to Y.

The default setting for this project default is N.

(When selecting option Update Inquiry or Create Supplement in the inquiry cycle in screen P.30.01 Requisition Workload, either this update/creation is performed immediately or screen P.30.03 Inquiry Assignment is called. Whether the screen is called or not depends on whether new line items have been released to procurement or not. If this project default is set to N, the screen is only called if new line items have been released.)

This project default is only used for requisition supplements, not for revised inquiry only requisitions.

  • Module(s) affected by this setting: P3001

  • Default value: N

  • List of Values: N/Y