This project default specifies the origin or department that is responsible for or dedicated to the project.

Origins can be defined and maintained on A.10.33.

The material take off (MTO) needs this information to assign an origin to engineering requisitions.

In addition, this project default is used as the default on the following screens: P.50.01 Agreements, P.60.01 Tagged Items Planning, P.60.03 Requisitions Planning, P.60.06 Budget Results, and R.30.01 Maintain Requisitions.

This default can be overwritten.

  • Module(s) affected by this setting: OPI1001, P3001, P5001, P5007, P6001, P6003, P7072, R3001

  • Default value: ./.