ZP_SET_MAN - Intergraph Smart Materials - Version 10.1 - Administration & Configuration - Hexagon

Intergraph Smart Materials Classic Administration (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Administration & Configuration
Smart Materials/Smart Reference Data Version
10.1

This project default is used to control the display of the forecasted date on the P.70.72 Expediting Details screen.

If ZP_SET_MAN is set to Y, when the forecasted delivery date on Window 2 is changed, the internal manual indicator is set and the field is shown with a cyan background.

If the project default is set to N (default), the internal manual indicator and color are not set when the forecasted date is changed.

  • Module(s) affected by this setting: P7072

  • Default value: N

  • List of Values: N/Y