PO Supplement Handling; only creation of change orders or splitting of positive and negative quantities on POs and COs.

With this project default, you control the order supplement handling.

If it is set to N (default), only the first purchase order created for an engineering requisition is of type PO. All further supplements will be of type CO regardless of whether you are increasing or decreasing quantities.

If the project default is set to Y, order supplements of type PO are created for positive quantities and additional / new line items, order supplements of type CO for negative (shortage) quantities.

This project default cannot be set on the discipline level.

This project default cannot be set to Y for projects that are created after 01-Jun-2012. The functionality controlled by this project default is obsolete and is not available for new projects.

  • Module(s) affected by this setting: P3001, P3002, P3004, P5007

  • Default value: N

  • List of Values: N/Y