When you change the source files for Smart Drawings, you must run Update on the Smart Drawings first, and then re-publish them to SmartPlant Foundation.
-
Select the project containing the corresponding Smart Drawing to update.
-
Modify the source files as required, or copy the modified source files into the current source file location.
-
Click Drawings to go to the Drawings View, and then select the Smart Drawing to update in the Smart Drawings Grid.
-
Click Update to update the drawing immediately.
-OR-
Click the Update drop-down menu, and then select Schedule Update. -
From the Schedule Update Dialog, create a job and select the date, time, and frequency for the update. See Schedule Jobs.
-
(Optional) Click Revise to create a new revision. Unless the change affects your revision scheme, you do not have to run Revise before publishing.
-
Click Publish to send the Smart Drawing back to SmartPlant Foundation, which automatically increments the version of the Smart Drawing document.