Exporting and Importing a Project - Intergraph Smart Instrumentation - 13.1 - Administration & Configuration - Hexagon PPM

Intergraph Smart Instrumentation Administration

Language
English (United States)
Product
Intergraph Smart Instrumentation
Search by Category
Administration & Configuration
Smart Instrumentation Version
13.1

These procedures are only available from version 13.1 HF7.

The Import/Export process (once started) continues even if you close the Administration Module. The Administration Module continues to run in the background. To close the Administration Module before the Import/Export process is complete or after the process is completed, use the Window's Task Manager to close the Administration Module.

As an Owner Operator/EPC-Project Mode you can export a project for use by an external contractor. This allows your external contractor to add and change items to your project "Off-Line" without gaining access to the your project database. As there is no external interaction with your database this creates a more secure environment for you and your external contractor. When the contractor has finished work on the project he returns the file where you can Import the file and check the data before merging it back to the project database.

  • Any specification custom views associated with your exported/imported project are not automatically transferred with the DDTI. To export/import your specification custom views, see Import and Export Specification Custom Views with a Project.

  • A DDTI backup file and a DDTI offline package file contain different data and therefore are not interchangeable, a package file cannot be used to initialize a domain or a domain backup file to export/import a package.