Start the Administration module and log on as Domain Administrator.
-
Do one of the following:
-
Click Activities > Project Activities.
-
Click
.
-
-
On the Project Activities dialog box, select Project Center.
-
Click Edit.
-
From the Project Administrator list, select a Project Administrator.
The Plant box displays All Plants. This option is view-only because Project Center is always associated with all the plants that exist in the current domain.
-
If needed, select a workflow option for Project Center.
Once you create the project schema you cannot change this selection.
-
If needed, type additional information in the Notes box.
-
Click Apply.