Start the Administration module and log on as Domain Administrator.
-
With the Domain Administration window open, click Activities > Preferences Management.
-
On the Preferences Management dialog box, from the Project list, select a project.
You can also select the DEFAULT PREFERENCES option from the Project list and set the default preferences which you can use when copying preferences to existing projects or As-Built or EPC-Project Mode. When you create a new project, it automatically receives the default preferences.
-
Click Advanced.
The advanced preferences cannot be applied to actions performed by the Import and Export preferences of Smart Instrumentation.
-
On the Advanced Project Preferences dialog box, do the following:
-
To allow users to set a preference for a Smart Instrumentation option in the current project, select Enabled next to the appropriate preference option.
-
To prevent users from setting a preference for a Smart Instrumentation option in the current project, clear the Enabled check box next to the appropriate option.
-
Select the Enable all check box to make all the preference options available for customization in the current project.
-
-
Do one of the following:
-
Copy To — to copy the current project preferences to other projects in the owner operator domain or EPC-Project Mode.
-
Copy From — to overwrite the preferences in the project you have selected in the Preferences Management dialog box.
-
-
Click Copy.
-
Click OK to save the settings and close the Advanced Project Preferences dialog box.