Which color definitions are available to filter the Materials information?

Smart Construction delivers the following browser color definitions:

Color definition

Purpose

ETA greater than ROS

Indicates if materials are estimated to arrive at the site after the Required on Site (ROS) date.

Insufficient quantity

Displays materials that have an on-hand quantity less than the BOM quantity.

Not on hand and no ETA

Displays materials that are not on hand and do not have an estimated time of arrival (ETA).

  1. Click Materials on the Home Page.

  2. Select a property from the Property box.

  3. Type search criteria in the Search box.

    You can use wildcards to narrow search results. ? finds any single character. * and % find any string of characters.

  4. Click Execute Search to view search results.

  • Items are highlighted and a warning displays when the following occurs:

    • The materials forecast indicates that the BOM Qty is more than the quantity of materials On Hand at the construction site.

    • The materials forecast indicates that the ETA of materials occurs after the Planned Start Date.

    • The materials forecast indicates that the ETA of materials occurs after the Req on Site date.

    • The materials forecast indicates that the Req on Site date occurs after the Planned Start Date.

    • The materials forecast indicates that the item is not on-hand and has no ETA.

  • Click a column heading to sort the column in ascending or descending order.