Run a materials forecast for an IWP - Intergraph Smart Construction - 8 - Reference - Hexagon PPM

Intergraph Smart Construction Retired Feature Reference

Language
English
Product
Intergraph Smart Construction
Search by Category
Reference
Smart Construction Version
8
  1. Click Work Packages on the project home page.

  2. Select an IWP from the Work Packages browser.

  3. Click Materials.

  4. Click the Forecast tab.

  5. Click Run Forecast.

  • Drawings must be added to the IWP in order to run a materials forecast.

  • You can forecast specific components based on the IWP purpose. Administrators must configure which work steps consume materials in the rules of progress. For more information, see Specify which work steps consume materials.

  • A warning displays when the following occurs:

    • The materials forecast indicates that the BOM Qty is more than the quantity of materials On Hand at the construction site.

    • The materials forecast indicates that the ETA of materials occurs after the Planned Start Date.

    • The materials forecast indicates that the ETA of materials occurs after the Req on Site date.

    • The materials forecast indicates that the Req on Site date occurs after the Planned Start Date.

    • The forecast data is out of sync with its associated drawing. Run the forecast again to clear the warning.