Cost codes can be configured in Smart Construction for cost account reference. Cost codes can be assigned to components based on the work package purpose. For example, a spool can have one cost code assigned for installation activities, and a different cost code assigned for painting activities. Cost codes are supported primarily for reporting and data exchange with other systems such as internal tracking systems.

  1. Open the ROP Configuration.xlsm workbook. For more information on managing configuration files for Smart Construction, see Manage Template Files for SmartPlant Construction.

  2. Enable the macro content for the workbook.

    1. On the Security Warning bar, click Options.

    2. Select Enable this content on the Microsoft Office Security Options and click OK.

  3. Select a rate table tab to open a rate table worksheet.

  4. Add a new column for the cost code.

  5. In the purpose and work step column, define a purpose for the cost code using the syntax $[Purpose].

    The IWP purpose must be spelled exactly the same as the purpose defined in the FIWP purposes enumerated list. For more information, see Configure Work Package Disciplines and Purposes.

  6. Type a value for the cost code for each lookup value.

    code code example

    The cost code must be spelled the same as the value in the Code box in the SmartPlant Foundation Desktop Client. Use the value in the Code box.

  7. Save your changes in the workbook file.

  8. Open the Main tab of the workbook.

  9. Click Generate Configuration File to generate the XML mapping to be used during retrieve.

  10. Verify the XML file generated to the location you specified when you checked out the files.

    If generating rules of progress data for the first time, attach the ROP Configuration.xlsm workbook and XML file to the Rules of Progress configuration document in the SmartPlant Foundation Desktop Client. For more information, see Attach the ROP Configuration workbook and XML files to the Rules of Progress configuration document

  11. Check in and sign off the ROP Configuration.xlsm workbook in the SmartPlant Foundation Desktop Client. For more information on managing configuration files for Smart Construction, see Manage Template Files for SmartPlant Construction.