Smart Construction provides the ability to automatically assign work steps to components in IWPs, along with their man hours and rates. These work steps form the basis of determining the completion status of an IWP. Administrators can configure rules of progress data to generate and associate work steps with register components and tagged items.

The register class must be specified in the Component Class row in the ROP Configuration.xlsm workbook.

For more information on configuring the rules of progress, see Configure the Rules of Progress.

For register-specific rules of progress information, see Delivered Smart Construction component register templates.