adjustment factor - Intergraph Smart Construction - Hotfix 14 - Help - Hexagon

Intergraph Smart Construction Help

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
8
SmartPlant Foundation / SDx Version
10

Conditions, such as weather or elevation, can affect the performance and productivity of a construction site. An adjustment factor can be applied to a project, individual IWPs, and individual work steps to compensate for any influencing conditions. Adjustment factors calculate the number of hours required to perform a task under project conditions, compared to the number of hours required to perform the same task under standard conditions.