The report section on the Work Package manager generates reports and also provides an option to select the Detail level of the report. You can select the level of details in a report from the options in the list.
In a work package report you can view the construction progress by system, work package, and also work package steps level. You can view these columns in a report:
-
Work Package ID (WP ID)
-
Description
-
Plan WTV
-
Budget MH
-
Actual WTV
-
Earned MH
-
Cost based WTV % Progress
-
MH Base (MH) % Progress