Sets options for sequencing names in a spool, pipeline, or pipe run.
Grouping/Sequencing Object Type
Select by what you want to sequence. You can select pipeline, pipe run, spool, or WBS item. This option defines the collection of target objects to be sequenced, and defines the boundaries of the sequencing.
Cancel
Reset the ribbon options.
Finish
Orders the object names using the options that you have set.
Target Object Type
Select what you want to re-sequence (rename) in the selected grouping.
Name Rule
Select the naming rule to use to rename the target objects.
Sequencing Type
Defines the logical order to use to define the sequence number part of the name.
Flow Direction
Begin sequencing at the furthermost upstream point on the line and proceed along the line with the flow direction. Subsequent branches are then processed according to their flow direction. The following example shows weld sequencing when using flow direction.
Topology
Start from the point on the primary header of the spool, pipeline, or pipe run with the highest coordinate value and work back along the target objects until all have been processed. Subsequent branches are then processed from the furthermost point into the branch connection. The following example shows weld sequencing when using topology.
Revision Control
Specifies what to do with existing sequence number when you run the command again. Select Retain existing numbers to keep the sequence number on any objects that have one, but create a new sequence number for objects that do not have a sequence number. Select Generate new numbers to discard all sequence numbers for the selected object and generate new numbers for everything.
Start Sequence Id
Specifies the sequence ID from which you want to begin the sequence. This option is available only when Generate new numbers is selected.