You can document a collection of parts that are assigned to a Work Breakdown Structure (WBS) item with individual isometric drawings. This topic describes the workflow for assigning parts to the WBS item and creating isometric drawings from the WBS information.
-
In the Piping task, assign the piping objects to an active project using Project > Claim. See Claim objects in the Common User's Help.
-
After assigning objects to an active project, assign them to a WBS item using Project > Assign to WBS. See Assign objects to a WBS item in the Common User's Help.
-
In the Drawings and Reports task, set up a Drawings by Query Manager component with the following options:
-
Select the Catalog Filters > Default Filters > SP3D Object Filters > Object Types > Common > WBS Items > WBS Items - Iso Drawing filter
-
Select the WBS Iso - Fabrication package.
-
-
Right-click the Drawings by Query Manager component and select Run Query.
-
Right-click the WBS Iso - Fabrication component and select Create Drawing(s).
-
Right-click the WBS Iso - Fabrication component and select Update Now to update the WBS Isometric drawing.
-
After the drawing updates, right-click the drawing and select Edit.