Assign objects to a WBS item - Intergraph Smart 3D - Administration & Configuration - Hexagon

Intergraph Smart 3D Integration - SmartPlant Foundation

Language
English
Product
Intergraph Smart 3D
Subproduct
Integration
Search by Category
Administration & Configuration
Smart 3D Version
13.1
SmartPlant Foundation / SDx Version
10
  1. Select the active WBS project in the Active Project box on the main toolbar. If the appropriate WBS project does not appear in the list, select More to open the Select Active Project Dialog.

  2. Select objects in the model by clicking in a graphic view, dragging a fence around objects, or selecting by filter.

    SHARED Tip When assigning a pipe run to the WBS item, you must select the entire pipe run. Use QuickPick to help with selecting the entire pipe run.

  3. Select Project > Assign to WBS.

  4. On the Assign to WBS Dialog, specify Workspace or Database to update the hierarchy of WBS items.

  5. Choose the WBS item to which you want the selected objects assigned.

  6. Select OK to create the relationships between the objects in the select set and the selected WBS item.

  7. Verify the relationship by selecting an object and doing one of the following:

    • Select an object and view the Relationship tab on its Properties dialog box.

    • Select the WBS item in the Workspace Explorer and select Select objects to assign on the WBS Item Edit Ribbon. All of the associated objects highlight in the graphical view.

    • Right-click the WBS item in the Workspace Explorer and select Select Nested. All the associated objects highlight in the graphical view.

  • If no as-built project exists, then a message indicates that the command requires an as-built project. You can create an as-built project in the Workspace Explorer by setting As-built in the Project Purpose field. For more information, see WBS Items and Projects.

  • If the select set contains objects that are already claimed to the parent project of the selected WBS item, or the objects are not claimed to another project through another WBS assignment, then the command highlights the objects and displays a message asking if you want to continue with the assignment on the other objects.

  • If some objects cannot be assigned because of assignment type problems, a message appears. Click Yes to continue with the valid objects.

  • If some of the objects are not valid because they are assigned exclusively, a message appears. Click Yes to change the assignment of the highlighted objects.