There are several methods to re-synchronize objects to SDx depending on the level of access defined for your Project As-Built role.
-
In Project Management, click Integration > SDx Synchronization Status Monitor Command to open the SDx Synchronization Status window.
-
Select a model in the Details Grid.
-
Click Re-synchronize in the Synchronize to SDx Status panel to open the Re-synchronize dialog.
-
If needed, select All Objects. By default, the Data Grid display is limited to data error objects.
-
Select the design objects that need to be marked for synchronization to SDx.
-
Click Re-synchronize to process the selected objects.
-
Click Yes in the message box.
When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx by the Share Service.
-
Click OK to close the message box.
-
Click Close to close the Re-synchronize dialog.
If you have the necessary level of access, you can also mark objects to be re-synchronized
using the SDx Synchronization Status Monitor. Click Start > Intergraph Smart 3D > SDx Synchronization Status Monitor to display the SDx Synchronization Status Options. Follow the remaining steps listed above to mark the design objects.
Smart 3D Change Management model
-
From within a Smart 3D design session, click Project > Re-Synchronize Command to open the Re-synchronize dialog.
-
Select a project in the list.
-
Select Error Objects or All Objects to specify the objects that display in the Data Grid.
-
Select the design objects that need to be marked for synchronization to SDx.
-
Click Re-synchronize to process the selected objects.
-
Click Yes in the confirmation box.
When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx by the Share Service.
-
Click OK to close the message box.
-
Click Close to close the Re-synchronize dialog.
Smart 3D Standard model
-
From within a Smart 3D design session, click Project > Re-Synchronize Command to open the Re-synchronize dialog. The software populates the Data Grid with data error objects, if any exist.
-
Select the error objects that need to be marked for synchronization to SDx.
-
Click Re-synchronize to process the selected objects.
-
Click Yes in the confirmation box.
When processing completes, the software displays a message that the selected objects have been marked and will be synchronized to SDx by the Share Service.
-
Click OK to close the message box.
-
Click Close to close the Re-synchronize dialog.