Before synchronizing subscribed projects, you must define SDx subscription settings. Otherwise, the software displays an error message.

  1. Open Project Management and select a model in the Project Management tree. The model that you select must be registered with a valid SDx server. See Create a new SDx registration.

  2. Click Integration > Synchronize Subscribed Projects from SDx Command to open the SDx Synchronization Status window. The window displays the synchronization progress for the selected model, alerts you to any errors that have occurred during the process, and notifies you when the process has completed.

  3. Review the Sync from SDx progress bar and Synchronize from SDx Status summary pane for the selected model. The Sync from SDx progress bar displays 100% when all subscribed projects are synchronized (1), and Sync Status Message displays a status message (2).