In a project, click Window > New > Project Management.
-
Right-click in the Project Management table and then click Show Merged Items .
-
Select the check box beside each item you want to release.
-
Do one of the following:
-
Click on the Project Management toolbar.
-
Right-click in the Project Management table and then click Release from Merge.
-
-
Do one of the following:
-
Click on the Project Management toolbar.
-
Right-click in the Project Management table and then click Apply.
-
After releasing from merge, the status of the items in the project becomes Scoped, that is, the items will be scoped after you click Apply again.