Before performing this scenario, ensure that you have completed all the prerequisite activities described in Sample Project Workflows.
-
In Project 1, check out Drawing D from the Plant.
-
Open Drawing D and do the following:
-
Claim the vessel and make a note of its Item Tag.
-
Claim the instrument OPC and the signal run connected to it.
-
Make a note of the instrument OPC's Item Tag and delete it to the Plant Stockpile.
-
Exit Drawing D.
Drawing D becomes Drawing D'.
-
-
In Project 1, create Drawing F.
-
Open Drawing F and do the following:
-
Place the instrument OPC that was placed in the Plant Stockpile after being deleted from Drawing D.
-
Place a Multiple Representation of the vessel.
-
Add an Equipment Name label to the vessel.
-
Exit Drawing F.
Drawing F becomes Drawing F'.
-
-
Attempt to check in Drawing F'.
Related Drawings error prevents check in.
-
Check in Drawings D' and F' together.
Key
|
|
Fetch drawing |
|
|
Continuity between procedure steps (an arrow indicates changes to the drawing or to drawing item data) |
Check in drawing |
|
Check-in unsuccessful |