Smart P&ID Project Statuses - Intergraph Smart P&ID - 10.0 - Administration & Configuration - Intergraph

Intergraph Engineering and Schematics Projects Configuration and Reference

Language
English
Product
Intergraph Smart P&ID
Search by Category
Administration & Configuration
Smart Electrical Version
10
Smart P&ID Version
10
Smart Engineering Manager Version
11

You can review the status of the active project using the Project Status command in Drawing Manager. The Project Status dialog box shows the status of the active project and tells you where the project is in its lifecycle.

A project status shows the stage of the project life-cycle.  Possible project statuses are:

  • Active — The initial state of a project right after its creation.

  • Completed — Indicates that all the work on the project items has been completed and that the items are ready to be merged back into the As-Built. You cannot claim items in a project whose status has been set to Completed or Merged.

    In a project, when searching for completed items in the Project Management window, it is possible to select the related items which have not been completed yet and to change their status to Completed.

  • Merged — Indicates that all the project items have been merged back into the As-Built.

  • Canceled — Indicates that the project has been canceled and it can be deleted.  Selecting this project status changes the status of the items in the project from Claimed to Scoped.

See Also

Modify Project Status in Smart P&ID