The following scenarios provide workflows for using projects in various configurations. You must perform the activities below before executing the workflows.
-
In Smart Engineering Manager, do the following:
-
Create a site.
-
Create a plant.
-
Associate the application.
-
Create plant groups that allow drawings.
-
-
In Smart P&ID Drawing Manager, create new drawings A - E and G, as shown.
-
In , do the following:
-
Open Drawing A.
-
Create Assembly A-1 and assign the item tags as shown.
-
Choose vessel type Equipment > Vessels > Vertical Drums > Short 1D 1C 1to1.
-
Place both OPC partners in the Plant Stockpile.
-
-
Make the assembly available in Catalog Explorer by opening Options Manager and running the Tools > Generate Symbol Images command.
-
Open Drawings B, C, D, and G and place Assembly A-1 in each of the drawings.
The software assigns unique item tags to the vessel, pipe runs, and OPCs in each drawing.
-
Open Drawing E and place the instrument OPC partner from Drawing D.
-
-
In Smart P&ID Drawing Manager, create a version of Drawing G and make a note of the version number (1).
-
In Smart Engineering Manager, do the following:
-
Enable projects for the plant.
-
Create three projects: Project 1, Project 2, and Project 3 and for each, set the Project Scope at the level of the unit in which you created the drawings.
-
Define Roles for each of the projects if not defined already.
-
-
In Smart P&ID Options Manager, under Settings, set the Claim Mode option to Shared.