When scoping As-Built items for a project, all the operating case data is copied together with the scoped items.
When creating a project, all the plant operating cases that exist in As-Built are created automatically in the new project.
Note the following information regarding plant operating cases when working with As-Built and projects.
Action |
As-Built |
Projects |
---|---|---|
Plant operating case management |
You can add, delete, and rename plant operating cases as needed (performed in Options Manager). If there are plant operating case inconsistencies between As-Built and an associated project, you have to make sure that the names of the operating cases in the projects are the same as in As-Built. |
You can add and rename cases as needed. You can delete only those cases that exist in the selected project only and they do not exist in As-Built.
|
Scoping |
All plant operating case data of the scoped items is automatically copied to the appropriate plant operating case of the project after the scoping is completed. If the governing case defined in a project is different from the governing case in As-Built, the governing case in the project remains unchanged when scoping items for that project. |
|
Merging |
All plant operating case data of the merged items is automatically copied to the appropriate As-Built operating case after the merging is completed. If the governing case defined in a project is different from the governing case in As-Built, the governing case in the project remains unchanged when merging items for that project. |
-
The software copies the item data to the appropriate operating case according to the ID of the relevant operating case. So, even if an operating case has been renamed at one stage or another, the software will still copy the item data to the appropriate operating case.
-
If you attempt to merge data in an operating case that was created in the project and this case, does not exist in As-Built, the software stops the merge process and prompts you to create an operating case in As-Built that has exactly the same name as in the project.
See Managing Plant Operating Cases and Synchronize Plant Operating Cases.