The buffer in the Project Management table allows you to make a preliminary selection of items that you want to scope.

  1. With the Project Management table in an As-Built plant open, right-click in the Project Management table and then select Show/Hide Buffer, or select PPM All Outputs Graphic.

  2. Drag the required items one-by-one to the buffer in the Project Management table. You can drag items from any of the following:

    • Electrical Index

    • Electrical Engineer

    • EDE

    • a schematic

    • a single line diagram

  3. In the Buffer, select the check boxes next to the items that you want to scope.

  4. Select PPM All Outputs Graphic on the Project Management toolbar or right-click in the Project Management table and then select Paste from Buffer.