Before performing this scenario, ensure that you have completed all the prerequisite
activities described in Sample Project Workflows.
-
In Project 1, check out Drawing B from the Plant.
-
Open Drawing B.
-
Fence select all items and claim the selected items.
-
Exit Drawing B.
-
In Project 2, fetch Drawing B from the Plant.
-
Open Drawing B.
-
Fence select all items except both OPCs and claim the selected items.
The claim status for the items indicates that they have already been claimed by another project.
-
Change the Tag Sequence Number for the vessel to 110.
-
Change the Construction Status of the vessel from New to Existing.
-
Exit Drawing B.
Drawing B becomes Drawing B'.
-
In Project 1, open Drawing B.
-
Place an Area Break around the vessel and Nozzle N1.
-
Place an Alt Dgn Press-Temp Equipment Label on the Area Break.
-
Select the Area Break, right-click, and on the shortcut menu, select Select Contents.
-
In the Properties window, if you cannot see the pressure and temperature properties, select Show Case Data for the Select Set to display those properties.
-
Assign Alt Dgn Max Press of 100 psi.
-
Assign Alt Dgn Max Temp of 101 F.
-
Exit Drawing B.
Drawing B becomes Drawing B''.
-
In Project 1, check in Drawing B'' with removal of the drawing from the project.
-
Select Project > Project Status.
-
Select Complete Project.
-
Select Merge Project to merge Project 1 into the Plant.
If you complete and merge Project 1, you will not be able to use it for the other workflows unless you delete and re-create Project 1. If you want to continue without deleting and re-creating the project, you should skip both the Complete and Merge operations until you have completed all of the workflows.
-
In Project 2, check out Drawing B'' without replacing the existing P&ID.
Drawing B'' becomes Drawing B' in Project 2.
-
In Project 2, attempt to check in Drawing B'.
Invalid Claim prevents check-in.
-
In Project 2, open Drawing B' and compare it with the drawing in the Plant.
-
Do the following:
-
Refresh Drawing B' for the Area Break and label and all other differences that result in invalid claims (see Compare and Refresh Drawing Versions).
-
Place a Revision Cloud around the Control Valve (FV-...) and the Actuator (ACT-...).
-
Place a Revision Triangle on the Revision Cloud. Label the Revision Triangle RT- 1.
-
Exit Drawing B'.
Drawing B' becomes Drawing B'''.
-
-
Check in Drawing B'''.
Key
|
|
|
Fetch drawing |
|
Continuity between procedure steps (an arrow indicates changes to the drawing or to drawing item data) |
|
Check in drawing |
|
Check-in unsuccessful |