Select Fetch
.
-
On the Fetch dialog, select the pertinent node in the Tree view if it is not already selected.
-
In the List view, select the drawing that you want to fetch.
-
Select History if you need to fetch a version of this drawing other than the current version.
-
On the Version History dialog, select the version that you want to fetch, and then select OK.
-
Select the Read-only option if you want to fetch a version of the drawing for review only.
-
(Optional) Enter appropriate comments in the Comments box.
-
Select OK. You can follow the progress of the fetch operation on the Fetching Drawings dialog. Select View Log if you want to examine notes from the fetch operation.
-
If you want to fetch a drawing version from another project and not from the Plant, select Open Database
on the Fetch dialog toolbar. On the Projects dialog, select the Plant or a project from the Available databases list, and then select OK.
-
You can open a read-only version of the drawing for review by selecting View. For more information about viewing drawing versions without fetching or checking them out, see Show the Version History of a Drawing.
If you are connected to SmartPlant Foundation and you have already fetched the drawing
with read/write permissions when you check the drawing out, the fetched version remains
intact and only its status changes to checked-out. That is, you cannot replace the
fetched version with the version in the Plant.