Run a Test Merge - Intergraph Smart P&ID - 11.0 - Administration & Configuration - Intergraph

Intergraph Engineering and Schematics Projects Configuration and Reference

ft:locale
en-US
Product
Intergraph Smart P&ID
Search by Category
Administration & Configuration
Smart P&ID Version
11
Smart Engineering Manager Version
12
  1. In the Project Management table (for As-Built), select the required project.

  2. On the Project Management table toolbar, select PPM All Outputs Graphic, or right-click in the Project Management table and then select Find Completed Items to see which items have been completed in the project.

  3. Right-click in the Project Management table and then select Test Merge.

The software generates a log file that shows any possible problems that might occur during the test merge. For details, see Generate Error Log Files in Smart Electrical Help.