  1. Open the project for which you want to view the status.

  2. On the Project Management window toolbar, select PPM All Outputs Graphic to open the Project Status dialog.

  3. In the Smart Electrical project status area, determine the current status of your project with respect to the plant. A check mark denotes the current status. Possible statuses include Active, Completed, Merged, and Canceled.

  4. Change the status of your project of your project as needed:

    To change an active project to completed, select Complete Project. This command is available only in the project when the initial project status is Active.

    To change a completed project back to active, select Reactivate. This command is available only in the As-Built when the initial project status is Completed, Merged, or Canceled.

    To merge a completed project into the plant, select Merge Project. This command is available only in the As-Built when the initial project status is Completed.

    To cancel an active project, select Cancel Project. This command is available only in the As-Built when the initial project status is Active, Completed, or Merged.

SHARED Tip When you change the project status to Completed, the software automatically sets the status of all the items in the project to Completed, except for registered reports and all documents (SLDs, schematics, miscellaneous drawings and electrical analysis SLDs). To include these items when merging the project, you must mark them manually as completed in a separate session.