Before performing this scenario, ensure that you have completed all the prerequisite activities described in Sample Project Workflows.

  1. In Project 1, check out Drawing D from the Plant.

  2. Open Drawing D and do the following:

    1. Claim the vessel and make a note of its Item Tag.

    2. Claim the instrument OPC and the signal run connected to it.

    3. Make a note of the instrument OPC's Item Tag and delete it to the Plant Stockpile.

    4. Exit Drawing D.

      Drawing D becomes Drawing D'.

  3. In Project 1, create Drawing F.

  4. Open Drawing F and do the following:

    1. Place the instrument OPC that was placed in the Plant Stockpile after being deleted from Drawing D.

    2. Place a Multiple Representation of the vessel.

    3. Add an Equipment Name label to the vessel.

    4. Exit Drawing F.

      Drawing F becomes Drawing F'.

  5. Attempt to check in Drawing F'.

    Related Drawings error prevents check in.

  6. Check in Drawings D' and F' together.

PPM All Outputs Graphic

Key



Check out drawing

Fetch drawing

Continuity between procedure steps (an arrow indicates changes to the drawing or to drawing item data)

Check in drawing

Check-in unsuccessful