Undo a Checkout - Intergraph Smart P&ID - Administration & Configuration - Intergraph

Intergraph Engineering and Schematics Projects Configuration and Reference (2019)

Language
English
Product
Intergraph Smart P&ID
Search by Category
Administration & Configuration
Smart Electrical Version
2019 (9.0)
Smart P&ID Version
9 (2019)
Smart Engineering Manager Version
10 (2019)

Before performing this scenario, ensure that you have completed all the prerequisite activities described in Sample Project Workflows.

  1. In Project 1, check out Drawing A from the Plant.

  2. Open Drawing A and do the following:

    1. Claim Vessel V-100.

    2. Find and replace Vessel V-100 with a 1 to 1 Parametric V Drum.

    3. Exit Drawing A.

      Drawing A becomes Drawing A'.

  3. In Project 2, fetch Drawing A' from Project 1.

  4. In Project 1, execute the Undo Checkout command on Drawing A', leaving Drawing A' in Project 1.

  5. In Project 2, open Drawing A' and do the following:

    1. Claim Nozzle N1.

    2. Change the Tag Sequence Number of the nozzle to 4.

    3. Exit Drawing A'.

      Drawing A' becomes Drawing A''.

  6. Check out Drawing A from the Plant to Project 2 without replacing the existing P&ID.

    Drawing A becomes Drawing A''.

  7. In Project 2, perform the following steps:

    1. Attempt to check in Drawing A''.

    2. View the check in log file.

      Unclaimed changes prevent check in.

  8. Open Drawing A'' and do the following:

    1. Claim Vessel V-100.

    2. Exit Drawing A''.

      Drawing A'' becomes Drawing A'''.

  9. Check in Drawing A''' with removal of the drawing from the project.

PPM All Outputs Graphic

Key



Check out drawing

Fetch drawing

Continuity between procedure steps (an arrow indicates changes to the drawing or to drawing item data)

Check in drawing

Check-in unsuccessful

Undo drawing check-out