Modify Project Status in Smart Electrical - Intergraph Smart P&ID - Administration & Configuration - Intergraph

Intergraph Engineering and Schematics Projects Configuration and Reference (2019)

Language
English
Product
Intergraph Smart P&ID
Search by Category
Administration & Configuration
Smart Electrical Version
2019 (9.0)
Smart P&ID Version
9 (2019)
Smart Engineering Manager Version
10 (2019)
  1. Open the project for which you want to view the status.

  2. On the Project Management window toolbar, click PPM All Outputs Graphic to open the Project Status dialog box.

  3. In the Smart Electrical project status area, ascertain the current status of your project with respect to the plant.

    SHARED Tip A check mark denotes the current status. Possible statuses include Active, Completed, Merged, and Canceled.

  4. Do any of the following to change the status of your project:

    • To change an active project to completed, click Complete Project. This command is available only in the project when the initial project status is Active.

      SHARED Tip When you change the project status to Completed, the software automatically sets the status of all the items in the project to Completed, except for registered reports and all documents (SLDs, schematics, miscellaneous drawings and electrical analysis SLDs).  To include these items when merging the project, you must mark them manually as completed in a separate session.

    • To change a completed project back to active, click Reactivate. This command is available only in the As-Built when the initial project status is Completed.

    • To merge a completed project into the plant, click Merge Project. This command is available only in the As-Built when the initial project status is Completed.

    • To cancel an active project, click Cancel Project. This command is available only in the As-Built when the initial project status is Active or Completed.