Exporting Networks and Activities - EcoSys - 1.1 - Customization & Programming - Hexagon

Integrating EcoSys with SAP Connector

Language
English
Product
EcoSys
Search by Category
Customization & Programming
EcoSys Version
1.1

It is also possible to export Network Headers and Activities from EcoSys to SAP. To enable this feature, set Project Export includeAdditionalStructures to True in the EcoSys Connect Settings Maintenance screen.

Activities must be assigned to a Network as the parent to export successfully.

The following Network fields are required to be set in EcoSys prior to export:

  • Cost Object ID

  • Cost Object Name

  • Cost Object Type = “Network”

  • SAP Plant

  • SAP MRP Controller

  • SAP Network Profile

  • SAP Network/Order Type

  • SAP Object Class

The following Network Activity fields are required to be set in EcoSys prior to export:

  • Cost Object ID

  • Cost Object Name

  • Cost Object Type = “Network Activity”

  • Cost Object Currency

  • SAP Plant

  • Activity Control Key

  • SAP Object Class

The following Network Activity fields are required to be set in EcoSys prior to export:

  • Cost Object ID

  • Cost Object Name

  • Cost Object Type = “Network Activity”

  • Cost Object Currency

  • SAP Plant

  • Activity Control Key

  • SAP Object Class