Follow the steps below to setup a project for export to SAP:
-
Create the project header in SAP
-
Run the EcoSys Connect Job: SAP Project to Cost Object Category
-
Create a project in EcoSys. The EcoSys Project ID does not need to match the SAP Project ID.
-
In the EcoSys Project Setup screen:
-
Assign the SAP project to the “SAP Project” field.
-
Set the “SAP Project Export” field to “Y”
-
Set the “SAP Mapping Method” to “Non-Mapped”. The project export currently only works with Non-Mapped projects.
-
-
In the EcoSys Project Structure screen, setup your WBS structure. The Cost Object ID should match the format that is compatible with SAP. Set the Cost Object Type to “WBS”.
-
Run the “SAP Project WBS Export” job. This will export the project structure to SAP.