Import planned costs totals from SAP to EcoSys as transactions. These totals are pulled from the following SAP tables: COSS (secondary costs, internal costs) and COSP (primary costs, external costs)
Job Details
-
Connect Job Name: SAP Planned Cost Totals Import
-
Connect Job Action: ITG SAPC Planned Cost Totals Import
Job Parameters
The parameters are specified in the EcoSys Connect Settings Maintenance screen under the "Default" SAP Import Group:
Parameter |
Default Value |
Description |
---|---|---|
ValueMultiplier |
|
Sets to -1 if incoming revenue values are negative. |
SAPLedgerNumber |
|
SAP ledger number is usually 00. Providing this value affords a performance gain as this field is part of database index. |
SAPVersion |
|
Specifies the VERSION value in SAP on which to filter. The default is to include all |
IsInternalPostings |
FALSE |
If True, read from the COSS table (internal postings), otherwise read from COSP (external postings) |
CostElementRangeStart |
|
Cost Element range starts. |
CostElementRangeEnd |
|
Cost Element range ends. |
CostElementCategoryRangeStart |
|
Cost Element Category range starts. |
CostElementCategoryRangeEnd |
|
Cost Element Category range ends. |
CostElementRangeMatch |
|
Cost Element range matches (either INCLUDE or EXCLUDE), which determines the behavior for cost elements in the specified range. |
Deprecated Parameters from SAP Adapter
Job Parameter |
Description |
forecastType |
Use separated Connect jobs for different forecast types |
Version |
Now specified in the API spreadsheet row filter |
includeAdditionalStructures |
This parameter is documented in the SAP Adapter but was never implemented |
startDate |
This parameter is documented in the SAP Adapter but was never implemented |
endDate |
This parameter is documented in the SAP Adapter but was never implemented |
commitBatchSize |
No longer applicable |
costObjectExternalIds |
Use SAP Import or SAP Import Group instead |